1. The definition of a project includes all of the following EXCEPT sausage cotton a beginning and end project staff predetermined desired outcome.
2. An example of one of the project phases is gathering information about the users needs. performing a cost/benefit analysis. planning designing the system interface.
3. The project planning phase includes all of the following activities, EXCEPT launching the project generating and evaluating alternatives defining the problem producing the project schedule.
4. The primary objective of the analysis phase is to analyze the capabilities and structure of the previous system. prioritize the alternatives for a new system determine the basic structure and approach for the new system understand and document the users requirements.
5. During the analysis phase, project team members do all of the following, EXCEPT gather information build prototypes design the network generate and evaluate alternatives.
6. The problem domain is the part of the systems development that refers to the problems associated with the computing environment the area of the users business that is being studied for a new system the problems of the organization of the company the area of the industry that results in more intense competition
7. Building prototypes can be part of every project phase, EXCEPT planning analysis design implementation
8. The design phase of the project includes which of the following design activities building the input screens for the database. providing bug fixes or patches. determining feasibility. end user support training.